Roof Update
These are the latest pictures of our sanctuary roof. We will also be replacing the shingles, some sheathing on the 1917 building (where the church offices are located). We hope the

Sanctuary Progress
Here are the latest updates on the sanctuary progress. Ceiling painting is complete and scaffolding is now down. The next steps are insulating the walls, framing, electrical and HVAC, and

Sanctuary Ceiling Progress
The reconstruction of our sanctuary is coming along at a great pace. The ceiling is just about complete. Scaffolding is coming down. Moulding is being put up. Some lighting has

Sanctuary Ceiling Update
Painting on the sanctuary ceiling is complete, along with the finished work around the “cloud” areas. Scaffolding is scheduled to come down next week. Next steps are building the east

Church Restoration as of 3/12/26
Sanctuary Ceiling Updates As you can see from the pictures, we are almost ready to paint the ceiling of the sanctuary. Our goal is to recreate the ceiling as close

Church Restoration as of 2/20/26
Sanctuary Ceiling Work continues in the sanctuary. Sheet rock is being added to the ceiling and wiring is being run. You can see the vents being added at the ends
Sanctuary Ceiling Updates
As you can see from the pictures, we are almost ready to paint the ceiling of the sanctuary. Our goal is to recreate the ceiling as close as possible to the way it was prior to the storm.