Sanctuary Updates
These are the latest pictures of the work being done in the sanctuary. As you can see, a lot of the drywall is going up. The HVAC piping is going […]
These are the latest pictures of the work being done in the sanctuary. As you can see, a lot of the drywall is going up. The HVAC piping is going […]
Roof Update-It’s finally done! Work on the roof of First Presbyterian Church is finally complete! We don’t need to worry about the spring rains! Thanks again to Wilson Roofing for
These are the latest pictures of our sanctuary roof. We will also be replacing the shingles, some sheathing on the 1917 building (where the church offices are located). We hope the
Sanctuary Updates-Work in the Sanctuary is progressing at a very steady pace now. The ceiling work is finished, except for all the lighting. The drywall is going up, and windows
The reconstruction of our sanctuary is coming along at a great pace. The ceiling is just about complete. Scaffolding is coming down. Moulding is being put up. Some lighting has
Painting on the sanctuary ceiling is complete, along with the finished work around the “cloud” areas. Scaffolding is scheduled to come down next week. Next steps are building the east
Sanctuary Ceiling Updates As you can see from the pictures, we are almost ready to paint the ceiling of the sanctuary. Our goal is to recreate the ceiling as close
Sanctuary Ceiling Work continues in the sanctuary. Sheet rock is being added to the ceiling and wiring is being run. You can see the vents being added at the ends
Sanctuary Scaffolding Scaffolding is being assembled in the sanctuary to work on the ceiling.
Basement The basement has been totally transformed with the floor being concrete instead of partially dirt. This has eliminated any remnants of mold and will keep everything dry. Strips of